SUMMARY OF MAJOR PROJECTS COMPLETED AND COMMISIONED IN FY 2013/2014

S/No Location Project Name County Project Scope Financier Project Cost No. Of People Served
1 MIGORI Migori Water Supply and Sanitation Project Migori Construction of 20,000 m3/day water supply system and construction of 9No. Abblution Blocks GOK & AfDB  1,257,039,970 (Water Supply) and 41,664,856.00 (Abblution Blocks)     200,000
2 KISUMU Kisumu Water Supply Project-LTAP-Package 1 Kisumu Construction of Transmision and Distribution pipeline of about 70km, reservours of capacity of 17,000m3 in Kisumu town. AFD & GOK 1,615,644,064      350,000
3 KISUMU Kisumu Water Supply Project-LTAP-Package 2 Kisumu Construction of Intake works, Raw Water Transmission main, mini hydropower at Kajulu and Treatment works of 48,000m3/day. Water to flow into Kisumu by gravity. AFD & GOK                 687,013,072.36  
4 KEROKA Construction of Short Term Water Supply Works-LVWATSAN II STI Nyamira Installation of pump sets for intake and treatment (4No.), Rehabilitation of: 3km rising mains, 2no. CFU, 1no. Clear water tank, laboratory, staff houses, chemical  dozing house, drainage works, supply/installation of water meters AfDB  166,000,000.00 20,000
5 ISEBANIA Construction of Short Term Water Supply Works-LVWATSAN II STI Migori Construction of: 2no. CFU 30m3/hr, elevated backwash tank, installation of 4no. Pumps, 1no. Clear water tank 100 m3,rising mains 4.8km 300mm dia,elevated storage tank 300m3,distribution lines 10km,drainage works, supply meters AfDB    20,000
6 KERICHO Construction of Short Term Water Supply Works-LVWATSAN II STI Kericho Rehabilitation of water treatment plant, replace cements of dozers, new backwash elevated tank, meter chambers, installations of meters, supply of lab. Equipment AfDB   30,000

 

Our Partners

 

 

 

Location

Lavictors House,
Off Ring road Milimani

Address

P.O. BOX 3325-40100,
KISUMU, KENYA

Email Us

customercare@
lvswaterboard.go.ke

Call Us

(+254) 057-2025128
(+254) 057-2025127

Follow Us