Projects / Services

 

KISUMU COUNTY

 

Name of Project Financier Intervention WSP Area Beneficiaries Budget (KES) Status Year of Completion FY of completion
Kisumu water supply -STAP AfD water supply KIWASCO Urban 426,400 305,242,562 Completed Aug-08 2007-08
Kisumu water supply, Emergency Works GOK+AFD water Supply KIWASCO Urban 105,860,554 Completed Dec-10 2010-11
Kisumu Water and Sanitation, Pums and  P/House GOK water Supply KIWASCO Urban 28,014,222 Completed Dec-10 2010-11
Kisumu water supply, LTAP 1 AFD water supply KIWASCO urban 1,615,644,065 Completed Dec-13 2013-14
Kisumu water supply, LTAP 2 AFD water supply KIWASCO urban 687,013,072 Completed May-14 2013-14
Kiusmu Water and Sanitation-STAP AfD sanitation KIWASCO Urban 16,614 104,684,280 Completed Aug-08 2007-08
Kisumu water supply, LTAP 3 AFD sanitation KIWASCO urban 110,759 1,284,550,145 Completed Nov-15 2015-16
Kisat Sewerage Expansion Project LVEMP Sanitation KIWASCO urban 53,000 102,000,430 Completed Jul-15 2015-16
Kisumu water supply, LVWATSAN-Package 1&2 EIB, AFD,ITF water supply KIWASCO urban 350,000 2,910,000,000 Planning Jan-20 2019-20
Kisumu water supply, LVWATSAN -Package3 EIB,AFD,ITF sanitation KIWASCO urban 120,000 3,500,000,000 Planning Jan-21 2020-21
Intergrated Water Resource Management Program KFW sanitation KIWASCO Urban 80,000 440,000,000 Planning Oct-21 2021-22
Total           11,083,009,330      

 

KERICHO COUNTY

                        Name of Project

Financier

Intervention

WSP

Area

Beneficiaries

Budget (KES)

Status

Year of Completion

FY of completion

Kericho Water Supply- LVWATSAN II-STI

AfDB

sanitation

KEWASCO

Urban

8,772

56,245,000

Completed

Dec-15

2015-16

Kericho Water Supply- LVWATSAN II- LTI

AfDB

sanitation

KEWASCO

Urban

204,000,000

Ongoing

Jun-18

2017-18

Kericho Solid Waste Management- Landfil

AfDB

sanitation

KEWASCO

Urban

11,250

14,437,643

Ongoing

Dec-17

2017-18

Water Sector Development Program ( Kericho)

KFW

water supply

KEWASCO

Urban

189,716

1,300,599,424

Ongoing

Dec-19

2019-20

Water Sector Development Program ( Kericho)

KFW

sanitation

KEWASCO

Urban

26,375

228,177,690

Ongoing

Dec-19

2019-20

Water Sector Development Program ( Litein)

KFW

water supply

TILWASCO

Urban

23,500

76,365,287

Ongoing

Feb-19

2018-19

Minihydropower Systems  for Water Supply in Litein

KFW

energy

KEWASCO

Urban

70,000

500,000,000

Planning

Oct-21

2021-22

Total

329,613

2,379,825,044

 

KISII COUNTY

Name of Project Financier Intervention WSP Area Beneficiaries Budget (KES) Status Year of Completion FY of completion
Kegati Water Treatment Expansion Project GoK Water supply GWASCO Urban 58,250 68,000,000 Ongoing Jun-17 2016-17
Water Sector Development Program ( Kisii) KFW water supply KEWASCO Urban 150,000 1,684,983,906 Ongoing Feb-19 2018-19
Water Sector Development Program ( Kisii) KFW sanitation GWASCO Urban 161,420 372,045,200 Ongoing Feb-19 2018-19
Kisii Water Storage ( Bonyunyu Dam ) Project - ORIO water storage GWASCO Urban -rural 230,000 1,838,000,000 Planning Jan-22 2021-22
Minihydropower Systems  for Water Supply in Kisii KFW energy GWASCO Urban 0 500,000,000 Planning Oct-21 2021-22
Total         599,670 8,463,029,106      

 

NYAMIRA COUNTY

Name of Project Financier Intervention WSP Area Beneficiaries Budget (KES) Status Year of Completion FY of completion
Keroka Water Supply- LVWATSAN II- STI AfDB water supply GWASCO urban 59,438 60,350,000 Completed Dec-15 2015-16
Keroka Water Supply- LVWATSAN II- LTI AfDB Water supply GWASCO Urban 460,000,000 Completed Mar-17 2016-17
Keroka Solid Waste  & Feacal Sludge AfDB sanitation GWASCO Urban 18,400 14,091,720 Ongoing Jun-17 2016-17
Water Sector Development Program ( Nyamira) KFW water supply GWASCO urban 110,000 372,045,200 Ongoing Feb-19 2018-19
Nyamira -Kisii Water Supply& Storage ( Bonyunyu Dam ) Project - ORIO water storage GWASCO Rural 230,000 4,030,800,000 Planning Jan-22 2021-22
Total         417,838 4,937,286,920      

 

BOMET COUNTY

Name of Project Financier Intervention WSP Area Beneficiaries Budget (KES) Status Year of Completion FY of completion
Bomet Sewerage Expansion Project LVEMP Sanitation BOWASCO Urban 29,000 131,230,200 Completed Jan-17 2016-17
Bomet -Mulot Water Supply AFDB Water Supply BOWASCO Urban 243,488 1,600,000,000 Planning Oct-20 2020-21
Bomet Water Supply Project NBI water supply BOWASCO Urban 19,500 26,750,500 Completed Sep-12 2011-2012
Chepalungu water supply project EU water supply BOWASCO Rural 27,250 44,052,250 Completed Jun-11 2010-11
Total         319,238 1,802,032,950      

 

SIAYA COUNTY

Name of Project Financier Intervention WSP Area Beneficiaries Budget (KES) Status Year of Completion FY of completion
Siaya/Bondo Water Supply Project (ADB)- Lot 1 AfDB water supply SIBOWASCO urban 130,395 1,576,000,000 Completed Mar-17 2016-17
Siaya/Bondo Water Supply Project (ADB)- Lot 2 AfDB Sanitation SIBOWASCO urban 29,600 629,000,000 Completed Jun-16 2015-16
Boro-Kanyaboli Water Supply Project KOICA water supply SIBOWASCO rural 87,000 400,000,000 Proposed Jun-23 2022-23
Ugunja/Ukwala/Sega Water Supply AFDB Water Supply SIBOWASCO Urban 72,390 1,100,000,000 Planning Oct-21 2021-22
West Uyoma Water Supply JPNCF Water Supply SIBOWASCO Rural 31,600 45,321,426 Completed Dec-15 2015-16
Asembo Ndori Water Supply Project -Phase I KOICA Water supply SIBOWASCO Rural 83,808 55,000,612 Completed Apr-10 2010-11
Asembo Ndori Water Supply Project -Phase II KIDP Water suply SIBOWASCO Rural 47,941,616 Completed Feb-11 2011-12
Asembo Nadori Water Supply Project-Phase III JNPCF Water Supply SIBOWASCO Rural 94,234,256 Completed Jun-11 2011-12
Asembo Ndori Sanitation JNPCF Sanitation SIBOWASCO Rural 1,200 1,530,000 Completed Jun-11 2011-12
East Uyoma Water Supply Project JPNCF Water supply SIBOWASCO Rural 12,000 43,000,000 Completed May-14 2013-14
Bondo Town Water Supply -LVWATSAN I UN-Habitat Water Supply SIBOWASCO Urban 25,203 26,000,000 Completed Feb-12 2011-12
Total         473,196 4,018,027,910      

 

HOMA-BAY COUNTY

Name of Project Financier Intervention WSP Area Beneficiaries Budget (KES) Status Year of Completion FY of completion
Suba Rural Water and Sanitation Project KIDP water supply Community Rural 17500 41,000,000 Completed Mar-10 2009-10
Homa Bay Sewerage Expansion Project LVEMP Sanitation HOMAWASCO urban 41,000 86,000,000 Completed Mar-17 2016-17
West Karachuonyo Water Project KIDP water supply HOMAWASCO rural 79,410 91,000,000 Ongoing Apr-17 2016-17
Homa Bay Water Supply Rehabilitation Project UN HABITAT water supply HOMAWASCO urban 14,250 46,000,000 Completed Dec-12 2012-13
Mbita Water Supply and Sanitation Project (LVWATSAN III) AfDB water supply HOMAWASCO urban 86,000 600,000,000 Proposed Jun-22 2021-22
Oyugis-Kendu Bay Water Supply Project AfDB water supply HOMAWASCO urban 110,000 600,000,000 Proposed Jun-19 2018-19
Homa Bay Water Supply Improvement FINEXPO water supply HOMAWASCO urban 83,000 1,000,000,000 Planning Sep-20 2020-21
Homa bay Wastewater (Trilateral Program) KFW sanitation HOMAWASCO urban 46,000 800,000,000 Planning Sep-21 2021-22
Kendu - Bay -Oyugis AFDB Water Supply HOMAWASCO Urban 138,944 1,800,000,000 Planning Oct-21 2021-22
Rangwe Water Supply Project- Phase 1 GOK Water supply HOMAWASCO Rural 15,000 52,369,259 Completed Dec-16 2016-17
Rangwe Water Supply Project- Phase 2 GOK Water supply HOMAWASCO Rural 24,000,000 Ongoing Feb-18 2017-19
Kanyadhiang Water Supply Project UNICEF Water supply SIBOWASCO Rural 28,949 58,148,648 Completed Jun-14 2013-14
Sindo Water Supply Project KIDP Water Supply HOMAWASCO Rural 12,876 71,256,352 Ongoing Jun-17 2016-17
Total         672,929.00 5,269,774,259      

 

MIGORI COUNTY

Name of Project Financier Intervention WSP Area Beneficiaries Budget (KES) Status Year of Completion FY of completion
Migori water Supply project (ADB) AfDB water supply MIWASCO urban 124,000 1,257,039,970 Completed Jun-14 2013-14
Migori Sanitation Project AfDB Sanitation MIWASCO Urban 12,000 41,664,856 Completed Oct-13 2013-14
Awendo Water Supply Project KOICA water supply MIWASCO urban 68,000 255,000,000 Completed Apr-12 2011-12
 Isebania Water Supply- LVWATSAN II- STI AfDB water supply MIWASCO urban 20,728 49,589,506 Ongoing Dec-15 2015-16
 Isebania Water Supply- LVWATSAN II- LTI AfDB water supply MIWASCO Urban 80,329 440,780,700 Completed Mar-17 2016-17
Isebania Solid Waste  & Feacal Sludge AfDB sanitation MIWASCO Urban 12,250 39,589,506 Ongoing Jun-17 2016-17
Rongo Water Supply Project GoK Water supply MIWASCO Urban 28,500 45,000,000 Ongoing Jun-18 2017-18
Kehancha Water Supply Project AfDB water supply MIWASCO urban 54,000 300,000,000 Proposed Jul-22 2021-22
Total         399,807 2,428,664,539      

 

NANDI COUNTY AND NAROK COUNTY

NB: LVSWSB only covers one sub-county in each of the two counties

Name of Project Financier Intervention WSP Area Beneficiaries Budget (KES) Status Year of Completion FY of completion
Nandi Hills Water Supply Project AfDB water supply KAPWASCO urban 90,000 580,000,000 Proposed Jun-19 2018-19
Kilgoris – Lolgorian Water Supply Project AfDB water supply NAWASCO urban 88,000 300,000,000 Proposed Jun-19 2018-19
Total         178,000 880,000,000      

Our Partners

 

 

 

Service Provision Agreement

Location

Lavictors House,
Off Ring road Milimani

Address

P.O. BOX 3325-40100,
KISUMU, KENYA

Email Us

customercare@
lvswaterboard.go.ke

Call Us

(+254) 057-2025128
(+254) 057-2025127

Follow Us